★ Must-know
📌 Operational work is ongoing, whereas project work has a definite end.
📌 Project objectives are defined in the project charter, and a project is considered complete when its objectives are met; it is terminated if they are not met.
Further detail
Management by objectives (MBO) establishes clear, concise, well-articulated, realistic objectives, reviews them periodically, and implements corrective actions when deviations occur.
Project constraints can involve:
📌 A change to one project constraint can affect other constraints, so the project manager evaluates change impacts through integrated change control.
Ongoing operations continue; projects have a definite end.
★ Must-know
The Initiating Process Group formally authorizes a project and may start project selection; its outputs include the project charter, identified stakeholders, and a stakeholder management strategy.
The Planning Process Group develops the project management plan and project documents, assesses the knowledge areas, and provides a roadmap for accomplishing the project.
The Executing Process Group completes the work in the latest revision of the project management plan, focusing on managing people, following processes, and distributing information.
Monitoring and Controlling measures project performance against the project management plan and handles change requests, corrective actions, preventive actions, and defect repair.
📌 A project is closed only after closure activities are completed and formal sign-off confirms that the product is acceptable; the project manager can then release resources involved in closing it.
Further detail
🔄 The process sequence is:
The project manager is assigned during the Initiating phase, and high-level planning at this stage can include a high-level WBS, order-of-magnitude estimates, and high-level risk identification.
Project planning is iterative, and the plan should accommodate changes while its level of detail and planning effort remain appropriate to the project’s needs.
Start → Plan → Act → Check and Act → End.
★ Must-know
The project manager is accountable for project success or failure and integrates project components into a cohesive whole that meets customer needs.
The program manager manages related projects together to achieve results not obtainable by managing each project separately and ensures selected projects support organizational strategic goals.
The sponsor advocates for the project, secures support and funding, provides the project statement of work and initial-scope information, and grants the project manager authority as outlined in the project charter.
📌 In a matrix organization, the functional manager shares direction of individuals’ work with the project manager; in a project-centric organization the project manager directs the work, while in a functional organization the functional manager directs it.
Further detail
The project manager is assigned no later than project initiation, helps write the project charter, and is in charge of the project but not necessarily its resources.
The portfolio manager governs the projects or programs in a portfolio at the executive level, selecting and managing them for organizational value and return on invested resources.
During project closing, the sponsor provides formal acceptance of deliverables and supports collection of historical project records.
The project team can help identify stakeholders, requirements, constraints, assumptions, WBS elements, activity dependencies, estimates, and risks, and execute the project management plan.
★ Must-know
Further detail
The scope management plan should define in advance how scope will be determined, managed, and controlled, and the project manager should seek formal approval for a clearly defined scope.
Scope requirements should be gathered from all stakeholders, because relying on only a few stakeholders or only the sponsor can lead to an incorrect scope definition.
Gold plating, or adding extras beyond the agreed project scope, is not allowed.
Scope changes require integrated change management that considers effects on time, cost, risk, quality, resources, and customer satisfaction; the change originator updates a change request form and the change is tracked in a change control register.
For a software project, product scope can be a new workflow application that fulfills internal and external customer requirements, assessed by comparing the resulting application with its documented requirements and project scope statement.
At the end of a project or phase, completed work is compared with the scope baseline in the project management plan to assess whether scope has been completed successfully.
A scope management plan answers how scope will be achieved, which tools and organizational resources are needed, and how scope will be managed and controlled throughout the project.
The scope management plan may be iterated during planning: the project manager first decides how to define scope, then uses more complete project information to plan execution and control, with later planning such as human resources planning potentially prompting revisions.
Do all the work in scope—and only that work.
★ Must-know
Collect Requirements begins with identifying stakeholders, records them in a stakeholder register, and then gathers and documents their detailed requirements using methods suited to the project and stakeholders.
Requirements can be gathered through interviews, focus groups, facilitated workshops, brainstorming, nominal group technique, Delphi technique, mind maps, affinity diagrams, questionnaires and surveys, observation, and prototypes.
Further detail
Requirements may concern product or process needs, including quality, business processes, regulatory requirements, compliance, and project management, and should support stated objectives rather than be included merely because someone wants them.
Historical records and lessons learned from similar projects help identify relevant requirements, team expectations, and scope-definition mistakes to avoid.
📌 In the Delphi technique, experts provide anonymous responses that are compiled and recirculated for review until consensus, whereas nominal group technique ranks ideas during a meeting following brainstorming.
📌 Group decisions may use unanimity, dictatorship, majority support from more than half the members, plurality by the largest number of supporters when no majority exists, or consensus acceptable to the group.
★ Must-know
📌 Verify Scope obtains customer acceptance of completed deliverables, including interim deliverables, whereas Close Project or Phase obtains final acceptance of the project or phase as a whole.
Further detail
📌 A WBS is created top-down with team involvement; each level is a smaller piece of the level above, the first level is completed before further decomposition, and it includes no deliverables outside the project.
★ Must-know
PDM relationship types are:
Padding estimates is unacceptable; estimates should be reviewed periodically for achievability, padding, and risks, and the project manager is responsible for providing accurate and feasible estimates.
Further detail
📌 A milestone is an interim deliverable or schedule point, not the duration or timeline of an activity.
📌 Mandatory dependencies follow the natural flow of work or may be contractually required, discretionary dependencies are selected by the project manager and team and can be changed, and external dependencies depend on parties outside the project.
📌 A lead allows a successor activity to start before its predecessor is complete, whereas a lag is waiting time inserted between activities.
Activity estimates are more accurate when based on the WBS, prepared by the people doing the work, and informed by historical information.
Estimate to Complete should be recalculated periodically to ensure adequate time, funds, and resources remain available for the project.
★ Must-know
📌 Padding is an arbitrary extra time or cost added because an estimator lacks information, whereas reserves are calculated to address identified risks and unknowns through risk management.
📌 Analogous estimating uses expert judgment and historical information from similar projects or activities, whereas parametric estimating uses relationships between variables and activity outcomes derived from historical or other data.
Further detail
Estimators should ideally be the people doing the work, although project team members familiar with the work often estimate durations.
Padding is less likely when:
Padding hides uncertainty; reserves address identified risk.
★ Must-know
📌 Total float is delay possible without delaying the project end date; free float is delay possible without delaying a successor’s early start; project float is delay possible without delaying an externally imposed completion date.
Further detail
📌 A near-critical path has a duration close to the critical path, and the closer their durations are, the greater the project risk.
📐 Formula - Float can be calculated as or , and both formulas give the same result.
Critical-path activities have zero float, while delayed projects or projects with imposed dates can have negative float.
Fast tracking performs critical-path activities in parallel that were planned in series and can cause rework, increase risk, and require more communication.
Crashing compresses a schedule through cost and schedule trade-offs while maintaining project scope, and it always increases cost.
Resource leveling produces a resource-limited schedule and can lengthen the schedule and increase cost and other constraints.
★ Must-know
📌 Variable costs change with the amount of work, whereas fixed costs do not vary with the amount of work.
📌 Direct costs can be attributed to project work, whereas indirect costs are overheads that cannot be apportioned to a specific project or activity and may serve multiple projects.
📌 Contingency reserves address known risks remaining after risk responses, whereas management reserves address unknown risks.
Further detail
A rough order of magnitude estimate is generally made during project initiation and typically ranges from -50% to +50%, while a budget estimate is made during planning and ranges from -10% to +25%.
A definitive estimate is a refined project cost estimate for which some project managers use a range of ±10% and others use -5% to +10% from actual.
🔄 Cost aggregation rolls costs up through these levels:
📌 The 50/50 rule credits an activity as 50% complete when it begins and the remaining 50% when it finishes; the 20/80 rule assigns 20% at the start and 80% at completion, while the 0/100 rule assigns no credit until completion.
Activity costs roll up to work packages, control accounts, then the project.
★ Must-know
Further detail
📌 Philip Crosby described quality as “conformance to requirements” and popularized prevention over inspection and “zero defects”; Joseph Juran defined quality as “fitness for use” and advocated top-management involvement in quality issues.
W. Edwards Deming is associated with the 14 points of quality management and the Plan-Do-Check-Act cycle.
Gold plating adds value or scope beyond what the customer requested based on the team’s impression of what the customer values, and it is not recommended because it can create a gap in customer expectations.
Poor quality leads to:
Crosby’s conformance to requirements contrasts with Juran’s fitness for use.
★ Must-know
📌 Plan Quality defines project quality and how to achieve it; Perform Quality Assurance checks whether planned processes are followed; Perform Quality Control examines actual deliverables against planned quality.
📌 Control limits are set from organizational quality standards and calculated at plus or minus three standard deviations; specification limits express customer expectations or contractual requirements and are stated by customers.
📌 A process is out of statistical control if a data point falls outside control limits or if a non-random pattern occurs, such as seven non-random points on one side of the mean, even within the limits.
Further detail
Plan Quality uses these inputs:
The cited standards and their purposes are: ISO 9000 supports organizational quality procedures and their use, OSHA sets worker-safety standards in plants, the CISG governs international sales transactions
📌 Additional project-specific standards and procedures must not violate other relevant standards, and quality effort should be appropriate to project needs and balanced against other project constraints.
The seven basic quality tools are:
A Pareto chart orders results from most frequent to least frequent and applies the 80/20 rule: 80% of problems are attributed to 20% of causes.
Control limits describe process variation; specification limits describe customer requirements.
★ Must-know
Team development stages are:
A Human Resource Plan covers:
The conflict sources in descending frequency are:
📌 Confronting solves the underlying problem in a win-win way, compromising gives each party partial satisfaction in a lose-lose outcome, withdrawal postpones or avoids a decision, smoothing emphasizes agreement, collaborating incorporates multiple viewpoints, and forcing imposes one viewpoint at another's expense.
Further detail
📌 A responsibility assignment matrix cross-references team members with activities or work packages, while a RACI chart clarifies assignments as Responsible, Accountable, Consult, or Inform.
A project sponsor provides financial resources and may be a customer, senior manager, or another party.
Project manager power types and their bases are:
Forming → Storming → Norming → Performing → Adjourning.
★ Must-know
The project manager spends 85%–90% of their time communicating, and communication-related issues are among the most frequent problems faced by project managers.
🔄 Stakeholder management proceeds by:
Stakeholder analysis identifies stakeholders and assesses their impact or influence using the project charter, past-project records, brainstorming, interviews, and names suggested by existing stakeholders.
The Communications Management Plan is a component of the Project Management Plan and documents how communication will be managed and controlled.
📌 Interactive communication involves two or more people exchanging information and responding, push communication sends information without expecting feedback, and pull communication places information centrally for recipients to retrieve.
📐 Formula - The number of communication channels among people is .
Further detail
Power/interest grids and salience models classify stakeholders by factors such as authority, impact, influence, or requirements to guide what, how, and when to communicate.
The stakeholder management strategy, an output of Identify Stakeholders, determines whether stakeholders are managed individually or in groups and accounts for both positive and negative involvement.
About 55% of communication is nonverbal, and pitch and tone of voice also help convey a message.
The project manager spends about 85–90% of their time communicating.
Performance reports include: status reports on current performance against the baseline, progress reports on work accomplished, trend reports, forecasts, variance reports, earned value reports, lessons-learned documentation
Identify stakeholders → determine needs and influence → plan communication → communicate → manage expectations.
★ Must-know
📌 Risk tolerance is the degree or level of risk considered acceptable, whereas a risk threshold is the specific point at which risk becomes unacceptable.
📌 Threat response strategies are avoid, mitigate, and transfer; opportunity strategies are exploit, enhance, and share; acceptance can apply to both threats and opportunities.
Further detail
Risk categories include external risks such as government, regulatory, environmental, and market risks; internal risks such as service, customer satisfaction, cost, and quality risks; technical risks from technology changes; and unforeseeable risks, estimated at about 9–10%.
Business risk can result in either gain or loss, whereas pure (insurable) risk results only in loss.
Risk identification techniques include:
Quantitative risk analysis can use expected monetary value analysis, Monte Carlo analysis, and decision trees to assess risk exposure and support estimates of reserves, costs, schedules, and the likelihood of meeting project objectives.
Risk response planning documents residual and secondary risks, contingency and fallback plans, response owners, risk triggers, contracts, and contingency reserves.
Monitoring and controlling risks includes tracking triggers and residual risks, evaluating responses, identifying further responses, recommending corrective actions, reassessing risks, conducting risk audits, analyzing reserves, and updating project records.
Plan, identify, analyze, respond, then monitor risks.
★ Must-know
The four procurement processes are:
Procurement contracts must be formal, and a change management procedure is the means of adding an activity that is not already included in the contract.
Planning procurements involves: performing a make-or-buy analysis, creating the procurement management plan, creating a statement of work for each procurement, selecting contract types, preparing procurement documents, determining source-selection criteria
Making is favored when: the organization has an idle plant or workforce, the work involves proprietary information or procedures, the organization wants to retain control
Further detail
In centralized contracting, one procurement department and manager handle procurements for multiple projects; in decentralized contracting, a procurement manager is assigned full-time to one project and reports to its project manager.
Procurement documents may include:
A procurement process can take one to three months because sellers need time to review project needs and respond.
Buy to reduce constraints; make when idle capacity, proprietary work, or control favors in-house delivery.
★ Must-know
📌 A procurement statement of work describes what the final product should accomplish, a functional statement of work emphasizes the end purpose or results rather than specific procedures, and a design statement of work specifies precisely what work is to be done.
📌 Fixed-price contracts suit well-defined requirements and sufficient competition to establish a fair price, whereas cost-reimbursable contracts suit uncertain scopes whose costs cannot be estimated accurately enough for fixed pricing.
Further detail
Design statements of work are most commonly used in construction and equipment purchasing, while performance and functional statements of work are used for work not done before, such as information systems, information technology, and research and development.
A time-and-material contract pays the seller per hour or per item and is often used for services whose level of effort cannot be determined when the contract is awarded.
A purchase order is a simple fixed-price contract signed by one party, making it unilateral rather than bilateral.
📌 A cost-plus-fixed-fee contract pays actual costs plus a negotiated fee fixed before work begins, whereas a cost-plus-incentive-fee contract adjusts the fee according to whether specified performance objectives are met.
📌 A cost contract pays the seller no fee, whereas a cost-plus-percentage-of-cost contract pays all costs plus a percentage of costs as a fee.
A fixed-price incentive-fee contract adjusts seller profit as performance targets are met, while a fixed-price award-fee contract adds a performance-based award whose total possible amount is determined in advance.
A sharing ratio describes how cost savings or overruns are shared between buyer and seller, and the point of total assumption in a fixed-price incentive-fee contract marks the point above which the seller bears all cost-overrun loss.
★ Must-know
📌 An RFP requests a detailed proposal describing how and by whom work will be done, an IFB usually requests the total price for all work, and an RFQ requests a price per item, hour, meter, or other unit.
Negotiations aim to obtain a fair and reasonable price and develop a good relationship with the seller, with scope, schedule, and price as the main items to negotiate.
Procurement closure occurs when a contract is completed or terminated early, and every procurement must be closed out regardless of how it ends.
Procurement closure includes:
Further detail
Procurement documents should include: seller background information and response instructions, source-selection criteria, pricing forms, the procurement statement of work, proposed contract terms and conditions
Source-selection criteria include:
📌 A single-source procurement selects a preferred seller directly, whereas a sole-source procurement has only one available source.
Evaluation methods include:
A legal contract requires:
The procurement manager or contract administrator has authority to change a contract; the project manager may request a change but needs the procurement manager's approval.
Termination may be for cause or for convenience, and the contract should contain termination provisions.
A procurement is closed after the seller receives the buyer's formal sign-off that the procured products are acceptable.
Administer performance and changes, settle claims, then verify, settle, pay, audit, and close.
Organizational Structure and Project Authority
| Structure | Work direction | Communication |
|---|---|---|
| Functional | Functional manager directs project work | Primarily within the same function |
| Project-centric | Project manager directs project work | Primarily within the same project |
| Matrix | Project manager and functional manager share authority according to matrix strength | Team members communicate with both managers |
Take a 69-question practice quiz on Project Management Foundations, with every answer explained.
1. Which description best defines a project?
2. A company continuously processes customer payments as part of its regular business, while a separate team is assigned to implement a new payment platform with a defined completion date. Which distinction applies?
Memorize the key concepts of Project Management Foundations with 96 flashcards.
What makes an effort a project?
It is a temporary effort to create a unique product, service, or result, with a definite start and end.
What distinguishes operational work from project work?
Operational work is ongoing, while project work has a definite end.
What does project management comprise?
It comprises five process groups and ten knowledge areas.