Managing Project Costs and Budgets Practice Quiz (11 questions)

All questions and answers

1. What is the central aim of cost management on a project?

Maximize project quality while expanding the available scope
Ensure sufficient project resources while controlling spending
Minimize spending even when resources are insufficient
Keep the schedule on track by controlling activity duration

Ensure sufficient project resources while controlling spending

Explanation

Cost management aims to ensure the project has sufficient resources while keeping spending under control. Maximizing quality, controlling duration, and minimizing spending regardless of resource needs each mistake its central purpose.

2. A project team is drafting its cost management plan. Which set of details should it specify to support consistent cost planning and control?

Funding sources, approval signatures, procurement methods, and supplier schedules
Activity durations, staffing levels, quality tests, and change-request procedures
Deliverables, acceptance criteria, stakeholders, and communication channels
Units, precision, thresholds, performance rules, and report types and frequencies

Units, precision, thresholds, performance rules, and report types and frequencies

Explanation

A cost management plan specifies units of measure, precision levels, control thresholds, performance measurement rules, and report types and frequencies. Deliverables and acceptance criteria concern scope, funding approvals concern authorization, and durations and quality tests do not replace these cost-planning details.

3. A project estimator reviews a set of methods before choosing one that uses optimistic, most-likely, and pessimistic estimates. Which technique is being considered?

Parametric estimation
Three-point estimating
Estimation by analogy
Bottom-up estimation

Three-point estimating

Explanation

Three-point estimating considers optimistic, most-likely, and pessimistic estimates. Parametric estimation uses statistical relationships, analogy uses costs from similar projects, and bottom-up estimation sums detailed task costs.

4. A project team has completed its final budget but has not yet received organizational approval. What must happen before the project starts?

The team must replace the budget with activity estimates
The project manager must begin controlling the budget
The experts must approve the schedule instead
The organization must approve the final budget

The organization must approve the final budget

Explanation

The organization must approve the final budget before the project starts. Completing the budget or having experts review it does not substitute for organizational approval, and budget control follows approval.

5. What does a sunk cost mean in project cost classification?

A cost independent of the quantity produced
A cost already incurred that cannot be recovered
A cost shared among resources used by several projects
A cost that changes proportionally with production

A cost already incurred that cannot be recovered

Explanation

A sunk cost has already been spent and cannot be recovered, so past spending should not determine whether future spending is justified. A shared resource cost is an indirect cost, not a sunk cost.

6. In the jewelry-store budgeting exercise, what planned budget results from adding the stated contingency to the activity costs?

€1,300 after adding €150 contingency to €1,150 in activity costs
€1,000 after adding €150 contingency to €850 in activity costs
€1,150 after adding €150 contingency to €1,000 in activity costs
€1,150 after adding €100 contingency to €1,050 in activity costs

€1,150 after adding €150 contingency to €1,000 in activity costs

Explanation

The listed labor, equipment, materials, and other costs total €1,000, and adding €150 contingency gives a planned budget of €1,150. The €1,300 figure incorrectly treats the resulting planned budget as the base cost before adding contingency.

7. What is the purpose of analyzing cost performance within a project's cost control cycle?

To record the work completed without assessing its cost implications
To establish the project's scope and approve its initial budget
To revise the schedule by reallocating resources among activities
To understand the causes of differences between measured costs and the plan

To understand the causes of differences between measured costs and the plan

Explanation

Analyzing helps the team understand why actual performance differs from the plan and informs appropriate corrective action. Comparing identifies differences, but does not itself explain their causes.

8. How do Planned Value and Earned Value differ in earned value analysis?

Planned Value budgets work scheduled by a given date, while Earned Value budgets work actually completed.
Planned Value measures the schedule difference, while Earned Value measures the cost difference.
Planned Value records money spent by a given date, while Earned Value records the remaining project budget.
Planned Value budgets completed work, while Earned Value budgets work scheduled for a given date.

Planned Value budgets work scheduled by a given date, while Earned Value budgets work actually completed.

Explanation

Planned Value represents the budgeted value of work that should have been completed by a given date; Earned Value represents the budgeted cost of the work actually completed. Actual Cost, rather than Planned Value, records the amount spent, so the option describing spending confuses the measures.

9. A project's actual costs are running higher than the budgeted value of the work completed. What effect does this have on its Estimate at Completion when calculated using earned value performance?

It raises the forecast total cost above the original budget.
It changes the remaining-cost forecast but not the total-cost forecast.
It lowers the forecast total cost below the original budget.
It leaves the forecast total cost equal to the original budget.

It raises the forecast total cost above the original budget.

Explanation

Since actual cost exceeds earned value, the cost ratio used to scale the budget upward is greater than 1, producing an Estimate at Completion above the Budget at Completion. A lower forecast would require the earned value to exceed actual cost under this calculation.

10. A team is seeking project funding and wants to distinguish money raised from outside the organization from resources supplied internally. Which proposed source is external financing?

Cash flow generated by the firm's operations
Voluntary contributions from project team members
Funds allocated from the firm's operating budget
A grant awarded by a public agency

A grant awarded by a public agency

Explanation

A grant is an external financing source, alongside options such as donations, sponsorship, crowdfunding, and loans. Operating cash flow and team contributions are internal sources, so they do not fit the team's external-funding category.

11. Which sequence represents the stages of project planning from defining the work through managing its costs?

Resources, schedule, scope, costs, control, budget
Scope, resources, schedule, budget, costs, control
Schedule, scope, costs, resources, control, budget
Scope, schedule, resources, costs, budget, control

Scope, schedule, resources, costs, budget, control

Explanation

Project planning proceeds from defining scope to setting the schedule, identifying resources, estimating costs, establishing the budget, and then controlling costs. The other sequences rearrange these stages, such as placing the budget before cost estimation.

Study with flashcards

Lock in the answers with 10 flashcards on Managing Project Costs and Budgets.

What does cost management aim to ensure while controlling spending?

Sufficient project resources.

What estimation techniques are listed for project costs?

Expert judgment, analogy, parametric, bottom-up, three-point, reserves, and cost-of-quality analysis.

Which sequence does project planning follow from scope through control?

Scope, schedule, resources, costs, budget, and control.

See the flashcards →

Read the study guide

Go over the full study guide for Managing Project Costs and Budgets.